Using the priority list T
6
, T
10
, T
9
, T
4
, T
2
, T
8
, T
7
, T
3
, T
1
, T
5
, schedule the project below with two processors.
[Graphs generated by this script: setBorder(60,30,60,30);initPicture(0,4,1,4); fontsize=14;fontstyle='none';marker="arrow";line([0,4],[1.5,4]);line([0,3],[1.5,4]);line([0,3],[1,3]);line([0,2],[1,2]);line([0,1],[4,2.5]);line([1.5,4],[3,4]);line([1.5,4],[3,3]);line([1,3],[2,3]);line([1,2],[2,3]);line([2,3],[3,3]);line([3,4],[4,2.5]);line([3,3],[4,2.5]);fontbackground='white';fontfill='blue';text([0,4],'T1 (4)','aboveleft');dot([0,4]);fontfill='blue';text([0,3],'T2 (3)','aboveleft');dot([0,3]);fontfill='blue';text([0,2],'T3 (2)','belowleft');dot([0,2]);fontfill='blue';text([0,1],'T4 (12)','belowleft');dot([0,1]);fontfill='blue';text([1.5,4],'T5 (11)','aboveleft');dot([1.5,4]);fontfill='blue';text([1,3],'T6 (7)','aboveleft');dot([1,3]);fontfill='blue';text([1,2],'T7 (9)','belowleft');dot([1,2]);fontfill='blue';text([2,3],'T8 (10)','aboveleft');dot([2,3]);fontfill='blue';text([3,4],'T9 (8)','aboveright');dot([3,4]);fontfill='blue';text([3,3],'T10 (6)','aboveright');dot([3,3]);fontfill='blue';text([4,2.5],'End','belowright');dot([4,2.5]);]
The finishing time is:
The total idle time in the schedule is:
Submit
Try a similar question
License
[more..]
Enter your answer as an integer or decimal number. Examples: 3, -4, 5.5172
Enter DNE for Does Not Exist, oo for Infinity
Enter your answer as an integer or decimal number. Examples: 3, -4, 5.5172
Enter DNE for Does Not Exist, oo for Infinity